In the Gantt module, you can convert a milestone to a Jira issue (and a [Jira issue to a milestone](https://appfire.atlassian.net/wiki/spaces/BGdcDRAFT/pages/2613559329)). Milestones cannot be converted to Jira issues in bulk.

> 📝 - A Jira issue converted from a milestone will have the start and end dates the same as the date of the milestone it was converted from.
> 📝 - Only milestones that were created or converted from [basic tasks](https://appfire.atlassian.net/wiki/spaces/BGdcDRAFT/pages/2613556042) can be converted to Jira issues.

## Context menu

1. Right-click a milestone or a diamond on the timeline to prompt the context menu.
2. Select **Convert to Jira issue**.

![A menu for converting a milestone to Jira issue.](media://5b1a6264-0a92-4a06-813b-9a361a9e36e5)

3. On the **Convert Basic task to Jira issue** screen:

- select Jira project from the dropdown
- select Jira issue type from the dropdown

4. Provide Jira issue details.
5. Click **Create** to finish the process.

## [Editor slider](https://appfire.atlassian.net/wiki/spaces/BGdcDRAFT/pages/2613571672)

1. Select a milestone or a diamond on the timeline to highlight it and prompt the editor slider.
2. From the editor slider, select **More actions** (**…**) > **Convert to Jira issue**.

![A menu for converting a milestone to Jira issue.](media://914bdcb8-47c3-41eb-8d21-83f1541a8825)

3. On the **Convert Basic task to Jira issue** screen:

- select Jira project from the dropdown
- select Jira issue type from the dropdown

4. Provide Jira issue details.
5. Click **Create** to finish the process.