## Calculate task progress

You can calculate the task progress using different fields and formulas. The progress can be displayed as a column, on the taskbar, and on the task details dialog once you click the taskbar.

For example: The SHPBOWM project is mapped to use the Time Tracking fields to calculate the progress (Remaining estimate and Spent time). The Select the property to build on (SHPBOWM-2) completed in 33% according to the following formula Time spent (1w)/Time spent + Remaining estimate (3w) * 100 %:

![Task progress shown in Gantt chart](media://e80b6e08-52c9-4301-8b53-b6de03ab8dd0)

## Configuration

You can configure the [progress field](https://appfire.atlassian.net/wiki/spaces/BGdcDRAFT/pages/2613546401) in the App Configuration, which requires Jira Administrator permissions. You can use one of the following options:

- Time Tracking Progress (Spent)
- Time Tracking Progress (Original)
- Custom number field <span style="color: #4d5156">— </span>values ranging from 0-100

## Displaying progress on the taskbar

To show the progress directly on the task, click **View** > **Progress**.

![Task progress bar displayed in the Gantt chart](media://a6d4e0e9-da5f-476f-b9a7-863ce02864e6)

Once enabled, the progress is displayed on both the child and parent taskbars:

![Progress bar displayed on parent and child tasks in Gantt chart](media://1b66bd2d-0592-4802-aa6d-7d6a962651e4)

## Updating task progress

You can update the progress of your task by editing the relevant fields (depending on the configuration). 

> ℹ️ Updating the progress using the slider on the taskbar feature is not available anymore in the new Gantt.