## Introduction

Adjust dependency settings at the top to modify the view. Click the **Browse dependencies **to expand the Infobar panel with dependencies. 

![gantt-dependencies-menu.png](media://2de84161-e00a-4abc-975f-171d85624f71)

## Display dependencies

### Expanded

Dependencies are displayed as arrows:

| **Link** | **Arrow** |
| --- | --- |
| Non ASAP | Blue arrow:<br>![Screenshot of the line for non-asap dependencies.](media://4c37559b-7ee1-4963-8b9a-61bd33ec42d7) |
| ASAP | Grey arrow:<br>![Screenshot of the line for asap dependencies.](media://84821c30-30bc-4a83-b8a2-c9093194d71f) |
| Soft dependency | Grey dotted arrow:<br>![Screenshot of the line for soft dependencies.](media://0d9d66f9-6493-4c82-ad84-383d148bbbca) |
| Out-of-view   
dependencies | ![Screenshot of the line for out-of-view dependencies.](media://b87c3ccd-f897-480d-b5d1-5ec9f1c23888) |
| Highlighted dependency | A dependency arrow is **in bold** when you highlight a dependency or task on the task tree to which the dependency applies.<br>![image-20240730-095137.png](media://770c748d-6532-4f9e-88da-92f44126daf1) |
| Not highlighted dependency | A dependency arrow's color is subdued when a task associated with the dependency is not highlighted.<br>![image-20240730-095429.png](media://4ce9c629-4261-4a4e-866a-5f050d272534) |

To see the outgoing dependencies list, click on a dot.

![Screenshot of the outgoing dependencies list in the Gantt module of BigPicture.](media://75ae498b-1e4a-47e1-af80-fe219044bd73)

To see the incoming dependencies list, click on a dot.

![Screenshot of the incoming dependencies list in the Gantt module of BigPicture.](media://d4b36820-577d-49ec-a7af-d49843d62de9)


#### Broken dependencies

If a strong dependency cannot be fulfilled because of other scheduling rules, it is displayed as an orange arrow (soft dependencies don't have a scheduling impact; therefore, they cannot be broken).

For example, a task can be done manually or in locked scheduling mode.

![broken-dependency-example.png](media://816db7ed-c412-45e4-9e90-97336976e663)

#### The number of dependencies exceeds the module capability

If the number of dependencies is too high to handle visually, they won't be shown as arrows.

### Collapsed 

If a task has any dependencies, they are indicated as a number in a dot.

![Screenshot of collapsed dependencies in the Gantt module.](media://cb025291-b58e-46c0-9266-df4674d31b6d)

To view dependency information, click on a dot.

- **Incoming dependencies** - the task is a target (endpoint) of dependencies. The source tasks (starting points of the dependencies) are listed.
- **Outgoing dependencies **- the task is a source (starting point) of outgoing dependencies. The target tasks (the endpoints of the dependencies) are listed.

### Task details - list of dependencies

In the task details dialogue, you can see the full list of outgoing and incoming dependencies. 

Click on a task on the Gantt chart to open the task details dialogue. The dialogue box can be expanded:

![Screenshot of the task details dialog in the Gantt module of BigPicture.](media://7e1dd4f4-f9a9-4760-8345-f29865e9a829)

### Infobar

You can view the full dependency list in the Infobar.

![Screenshot of all dependencies in the Infobar panel of the Gantt module.](media://ef3d9cce-cb30-4657-a537-4dffb47ca9bc)

## Dependencies and task dates

> Macro (excerpt)
> 
> When many tasks are linked by dependencies, and one of the tasks loses both dates (start and end dates), **dependencies are saved**. The arrow between tasks will temporarily disappear, but you can still check the dependency by switching to the **Collapsed** display and clicking on a number in a dot next to the task.
> 
> ![Screenshot of an example for a collapsed dependency on the Gantt chart.](media://74506ab3-c075-41b2-8d06-dd63e39fa513)
> 
> The arrow between tasks will appear once you assign at least one date to the task.
> 
> ![Screenshot of an example for a collapsed dependency with no end date on the Gantt chart.](media://8d0a9037-fd9f-4127-8b64-ead98d645e21)

## Out-of-view dependencies 

Out-of-view dependencies can't be displayed on the Gantt chart.

|  |  |
| --- | --- |
| A source or target task is in the scope of another box | Only one task is visible on the Gantt chart, while the other one is in a different box. As a result, dependency cannot be visualized.<br>The out-of-view status is indicated by:<br>- Crossed-eye icon in the Infobar.<br>- Crossed-eye icon in the task details dialog box under the **Inward** or **Outward dependencies**.<br>![Out-of-view dependency indicated in the task details dialog box.](media://e0810997-1fc2-4588-b29c-2d6b53a22fc3)<br>- Grayed out **Focus on the source/ target **option. A source or target task is in the scope of another box. As a result, it cannot be visualized on the Gantt timeline in the current box.<br>![A grayed out Focus on the source option in the Gantt iInfobar.](media://7cbbe915-3e9f-4f1d-a97b-4c11feecbbd1) |
| A source or target task is not visible because of active filters | Only one task is visible, while the other task is hidden because of active filters.  As a result, dependency cannot be visualized.<br>The out-of-view status is indicated by:<br>- Crossed-eye icon in the Infobar.<br>- Grayed out **Focus on the source/ target **option. A source or target task is in the scope of another box. As a result, it cannot be visualized on the Gantt timeline in the current box. |

 

  


> Macro (excerpt)
> 
> **Introduction**
> 
> Adjust dependency settings at the top to modify the view.
> 
> ![image-20240925-054904.png](media://46e06382-ed3c-47d2-a6c7-974a47c39873)
> 
> **Display dependencies**
> 
> **Expanded**
> 
> Dependencies are displayed as arrows:
> 
> | **Link** | **Arrow** |
> | --- | --- |
> | Non ASAP | Blue arrow:<br>![Screenshot of the line for non-asap dependencies.](media://4c37559b-7ee1-4963-8b9a-61bd33ec42d7) |
> | ASAP | Grey arrow:<br>![Screenshot of the line for asap dependencies.](media://84821c30-30bc-4a83-b8a2-c9093194d71f) |
> | Soft dependency | Grey dotted arrow:<br>![Screenshot of the line for soft dependencies.](media://0d9d66f9-6493-4c82-ad84-383d148bbbca) |
> | Out-of-view   
> dependencies | ![Screenshot of the line for out-of-view dependencies.](media://b87c3ccd-f897-480d-b5d1-5ec9f1c23888) |
> | Highlighted dependency | A dependency arrow is **in bold** when you highlight a dependency or task on the task tree to which the dependency applies.<br>![image-20240730-095137.png](media://770c748d-6532-4f9e-88da-92f44126daf1) |
> | Not highlighted dependency | A dependency arrow's color is subdued when a task associated with the dependency is not highlighted.<br>![image-20240730-095429.png](media://4ce9c629-4261-4a4e-866a-5f050d272534) |
> 
> To see the outgoing dependencies list, click on a dot.
> 
> ![Screenshot of the outgoing dependencies list in the Gantt module of BigPicture.](media://75ae498b-1e4a-47e1-af80-fe219044bd73)
> 
> To see the incoming dependencies list, click on a dot.
> 
> ![Screenshot of the incoming dependencies list in the Gantt module of BigPicture.](media://d4b36820-577d-49ec-a7af-d49843d62de9)
> 
> 
> **Broken dependencies**
> 
> If a strong dependency cannot be fulfilled because of [other scheduling rules](https://appfire.atlassian.net/wiki/spaces/DLP/pages/350421234), it is displayed as an orange arrow (soft dependencies don't have a scheduling impact; therefore, they cannot be broken).
> 
> For example, a task can be done manually or in locked scheduling mode.
> 
> ![broken-dependency-example.png](media://816db7ed-c412-45e4-9e90-97336976e663)
> 
> #### The number of dependencies exceeds the module capability
> 
> If the number of dependencies is too high to handle visually, they won't be shown as arrows.
> 
> **Collapsed **
> 
> If a task has any dependencies, they are indicated as a number in a dot. 
> 
> ![Screenshot of collapsed dependencies in the Gantt module of BigPicture.](media://8120217c-ca13-4e8e-8fdb-bc51795eb9d1)
> 
> To view dependency information, click on a dot.
> 
> - **Incoming dependencies** - the task is a target (endpoint) of dependencies. The source tasks (starting points of the dependencies) are listed.
> - **Outgoing dependencies **- the task is a source (starting point) of outgoing dependencies. The target tasks (the endpoints of the dependencies) are listed.
> 
> **Task details - list of dependencies**
> 
> In the task details dialogue, you can see the full list of outgoing and incoming dependencies. 
> 
> Click on a task on the Gantt chart to open the task details dialogue. The dialogue box can be expanded:
> 
> ![Screenshot of the task details dialog in the Gantt module of BigPicture.](media://7e1dd4f4-f9a9-4760-8345-f29865e9a829)
> 
> **Infobar**
> 
> You can view the full dependency list in the [Infobar](https://appfire.atlassian.net/wiki/pages/createpage.action?spaceKey=BPEdcDRAFT&title=000%20Infobar%20%28Gantt%29).
> 
> ![image-20240925-055018.png](media://51570219-9922-437d-b863-104c48d54f3e)
> 
> **Dependencies and task dates**
> 
> When many tasks are linked by dependencies, and one of the tasks loses both dates (start and end dates), **dependencies are saved**. The arrow between tasks will temporarily disappear, but you can still check the dependency by switching to the **Collapsed** display and clicking on a number in a dot next to the task.
> 
> ![Screenshot of an example for a collapsed dependency on the Gantt chart.](media://74506ab3-c075-41b2-8d06-dd63e39fa513)
> 
> The arrow between tasks will appear once you assign at least one date to the task.
> 
> ![Screenshot of an example for a collapsed dependency with no end date on the Gantt chart.](media://8d0a9037-fd9f-4127-8b64-ead98d645e21)
> 
> **Out-of-view dependencies **
> 
> Out-of-view dependencies can't be displayed on the Gantt chart.
> 
> |  |  |
> | --- | --- |
> | A source or target task is in the scope of another box | Only one task is visible on the Gantt chart, while the other one is in a different box. As a result, dependency cannot be visualized.<br>The out-of-view status is indicated by:<br>- Crossed-eye icon in the Infobar.<br>- Crossed-eye icon in the [task details](https://appfire.atlassian.net/wiki/spaces/DLPDRAFT/pages/296979735) dialog box under the **Inward** or **Outward dependencies**.<br>![Out-of-view dependency indicated in the task details dialog box.](media://e0810997-1fc2-4588-b29c-2d6b53a22fc3)<br>- Grayed out **Focus on the source/ target **option. A source or target task is in the scope of another box. As a result, it cannot be visualized on the Gantt timeline in the current box.<br>![A grayed out Focus on the source option in the Gantt iInfobar.](media://7cbbe915-3e9f-4f1d-a97b-4c11feecbbd1) |
> | A source or target task is not visible because of active filters | Only one task is visible, while the other task is hidden because of active [filters](https://appfire.atlassian.net/wiki/spaces/DLPDRAFT/pages/297959853).  As a result, dependency cannot be visualized.<br>The out-of-view status is indicated by:<br>- Crossed-eye icon in the Infobar.<br>- Grayed out **Focus on the source/ target **option. A source or target task is in the scope of another box. As a result, it cannot be visualized on the Gantt timeline in the current box. |