---
title: "Task progress"
canonical: "https://support.appfire.com/space/DLP/2211646597/Task%20progress"
format: markdown
---
> Macro (aura-html)

## Calculate task progress

You can calculate the task progress using different fields and formulas. The progress can be displayed as a column, on the taskbar, and on the task details dialog once you click the taskbar.

For example: The SHPBOWM project is mapped to use the Time Tracking fields to calculate the progress (Remaining estimate and Spent time). The Select the property to build on (SHPBOWM-2) completed in 33% according to the following formula Time spent (1w)/Time spent + Remaining estimate (3w) * 100 %:

![Task progress shown in Gantt chart](media://e6cb8b6c-1dfe-4d44-9c20-cb8f95ecbc68)

## Configuration

You can configure the [progress field](https://appfire.atlassian.net/wiki/spaces/DLP/pages/2212497305) in the App Configuration, which requires Jira Administrator permissions. You can use one of the following options:

- Time Tracking Progress (Spent)
- Time Tracking Progress (Original)
- Custom number field <span style="color: #4d5156">— </span>values ranging from 0-100

## Displaying progress on the taskbar

To show the progress directly on the task, click **View** > **Progress**.

![Task progress bar displayed in the Gantt chart](media://a9c835f6-3733-4f17-8013-9caff6c042ad)

Once enabled, the progress is displayed on both the child and parent taskbars:

![Progress bar displayed on parent and child tasks in Gantt chart](media://fae0607b-5323-4cc0-aac9-79939ddffd63)

## Updating task progress

You can update the progress of your task by editing the relevant fields (depending on the configuration). 

> ℹ️ Updating the progress using the slider on the taskbar feature is not available anymore in the new Gantt.