title: "Convert milestone to Jira issue"
canonical: "https://support.appfire.com/space/DLP/2212529814/Convert%20milestone%20to%20Jira%20issue"
format: markdown
---
> Macro (aura-html)

In the Gantt module, you can convert a milestone to a Jira issue (and a [Jira issue to a milestone](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918537200)). Milestones cannot be converted to JIra issues in [bulk](https://appfire.atlassian.net/wiki/spaces/DLP/pages/2212496212).

> 📝 - A Jira issue converted from a milestone will have the start and end dates the same as the date of the milestone it was converted from.
> 📝 - Only milestones that were created or converted from [basic tasks](https://appfire.atlassian.net/wiki/spaces/DLP/pages/2211352313) can be converted to Jira issues.

## Context menu

1. Right-click a milestone or a diamond on the timeline to prompt the context menu.
2. Select **Convert to Jira issue**.

![A menu for converting a milestone to Jira issue.](media://31467cb3-813c-4eaa-a0b5-4b6c69c6561f)

3. On the **Convert Basic task to Jira issue** screen:

- select Jira project from the dropdown
- select Jira issue type from the dropdown

4. Provide Jira issue details.
5. Click **Create** to finish the process.

## [Editor slider](https://appfire.atlassian.net/wiki/spaces/DLP/pages/2212528926)

1. Select a milestone or a diamond on the timeline to highlight it and prompt the editor slider.
2. From the editor slider, select **More actions** (**…**) > **Convert to Jira issue**.

![A menu for converting a milestone to Jira issue.](media://333743f9-6d53-40b9-9bab-5064b82ed60e)

3. On the **Convert Basic task to Jira issue** screen:

- select Jira project from the dropdown
- select Jira issue type from the dropdown

4. Provide Jira issue details.
5. Click **Create** to finish the process.