Plan delay reports provide information on task delays on all hierarchy levels, with a set **Baseline End Date **field.

![Plan delays window with one row highlighted](media://f0320e0c-2541-4412-94b3-f1f7913eafae)

Hold the pointer over a task name to display a tooltip with the task's status in round brackets.

Tasks are sorted by **End Date. **

## **Report configuration **

In the plan delays report, you can edit the report configuration to:

- show **only the open delayed tasks **versus the plan - to monitor current delays
- show the **closed delayed tasks** - to check the number of delayed tasks versus the plan after finishing the project