| Category | Feature description | Sneak peek |
| --- | --- | --- |
| Scheduling | **[Tasks without dates](https://appfire.atlassian.net/wiki/spaces/DLP/pages/315262798)**<br>Dates do not need to be specified when a new task is added to a box (either by creation or modification of scope definition). Tasks without dates are visible in the task tree (WBS) but aren’t shown on the Gantt chart until the start/end date is specified. Additionally, unscheduled tasks are visible in a [panel on the Resouces module](https://appfire.atlassian.net/wiki/spaces/DLP/pages/512328594).<br>**Note**: Existing tasks that have already been positioned on the timeline are NOT affected by the change.<br>The [Overdue](https://appfire.atlassian.net/wiki/spaces/DLP/pages/296851268) feature is NOT available for tasks that don’t have a start/end date. | ![image](media://f343f460-c9e7-4ddb-8800-b8ff12519b73)<br>![image](media://d25628e8-b83a-443f-9b97-c3d116588476) |
| **[Task dates (start/end) based on estimates - behavior](https://appfire.atlassian.net/wiki/spaces/DLP/pages/296851336)**<br>Change of a task duration or the estimate value results in a task being resized. The mapped value (either start or end) is updated. The other date doesn’t change (unless additional scheduling mechanisms apply)<br>Change of the start/end date value (behavior the same regardless of which value is mapped):<br>- change of the **start date** results in a task being moved.
- change of the** end date** results in a task being resized. The estimate field and task duration field reflect the change. The start date is unaffected. | n/a |
| BigTemplate | Tasks without dates can be exported<br>All tasks are exported:<br>- with dates (start/end)
- with one date
- without dates | n/a |
| Tasks without dates can be imported<br>All tasks are imported:<br>- with dates (start/end)
- with one date
- without dates<br>Note: validation check →  start date cannot be later than end date | n/a |
| Usability | After page refresh, the Gantt chart view returns to the same position on the timeline | n/a |