# Taskbar (old navigation)

<details>
<summary>Click to expand the guide</summary>

## Overview

The taskbars on the [Gantt timeline](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918701893) (Gantt chart) represent your project work items (for example, epics, Jira issues, and [basic tasks](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918405930)).

Each taskbar can immediately provide you with the following information:

- task start/end dates
- color (by default, the color is based on the task status)

![Gantt chart taskbars.](media://8565266a-7fc1-4f43-a5fe-4fb78fcb35f4)

If the task is scheduled or partially scheduled (it has only a start or end date), it will be visualized as a taskbar on the Gantt timeline. 

- The beginning of the taskbar marks the start date.
- The end of the taskbar marks the end date.
- If the start/end date is not defined, the relevant side of the taskbar is faded.

If you cannot see the exact date,[ zoom in](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918701893/Timeline+Gantt+chart#Zoom-in%2Fout) on the timeline or [snipe to its start/end date](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918701893/Timeline+Gantt+chart#Snipe-to-task-start%2Fend-date).

You can add an additional layer of information to the Gantt timeline by selecting the relevant option from:

![Menu options related to the Gantt taskbars.](media://6ef00be1-2a0e-4a02-bd4d-7477f4a8ef09)

- **View**
- **Taskbar**
- **Dependencies**

## View (option)

1. Click the **View** option.
2. From the menu, check one or several options:

- **Baselines**
- **Period warnings**
- **Progress**
- **Critical path**
- **Overdue**

### [Baselines](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918404564)

If you have baselines created for your tasks, they can be displayed as horizontal lines under the taskbars.

![A baseline under a taskbar.](media://cee75553-2067-490f-94d5-7a4c48c79a75)

### [Period warnings](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918832897)

The **Period warnings **option adds a yellow overlay to the taskbar to indicate a mismatch between the task's period and that of the child or parent task.

![Period warning on the taskbar.](media://307c7c32-5f26-458a-ac2c-1c987ca17ab5)

### Progress

The taskbar color gradually fills up as its progress advances.

![Progress on the taskbar.](media://2740b3df-9abb-4ad7-838a-700caa38272a)

### [Critical path](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918405060)

If you have created dependencies between the tasks, this option will change the color of the tasks on the critical path to red stripes. 

![Taskbar on the critical path.](media://10caa146-b60c-417d-aa13-d3f656d7de27)

### [Overdue](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918537803)

Enable this option to see tasks that were not completed on their due date. The color of the due taskbars changes to red, and the number in a red circle indicates the number of due days.

![And overdue taskbar.](media://a259009b-c47d-4efe-b657-504188bd3623)

## Taskbar (option)

1. Click the **Taskbar** option.
2. From the menu, check one or several options:

### Label position

The **Label position** determines where the task summary will be placed in relation to the taskbar. The task label can consist of the Key and/or Summary field values. 

> 📝 You must first check the **Key** and/or **Summary** in the **Show** options.

- Hidden (Removes the label leaving the taskbar blank (but still colored).
- On taskbar (displays the label on the taskbar. If the label is longer than the taskbar, the label is truncated)
- Next to taskbar (displays the label on the right side next to the taskbar)
- Smart labeling (displays summary on or next to the taskbar depending on whether the summary exceeds the taskbar length)

### Show

The **Show** options add more info on/next to the taskbar.

- Key [taskbar label]
- Summary [taskbar label]
- Other scope info (adds an indication on the taskbar when a task is in the scope of multiple boxes)

> ✅ This taskbar indication applies only to boxes of the **Own** [scope type](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918766536). 
> ✅ 
> ✅ If a task is in the scope of a sub-box, it belongs to multiple boxes but not multiple Own-scope boxes.
> ✅ 
> ✅ ![An icon indicating the task is in the scope of multiple boxes.](media://86aad27c-ca05-46da-bd98-fa7a599c93c1)

- Dates
- Assignee (adds the assignee avatar/icon)
- Priority (displays the priority icon taken from the built-in Priority field on the left side next to the taskbar)
- [Scheduling mode](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918831395) (displays the scheduling mode icon on the left side next to the taskbar)
- [Notes](https://appfire.atlassian.net/wiki/spaces/SPM/pages/2372665547)

### [Task color](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918636160)

Colors the taskbar by its status or by manually selected colors)

## [Dependencies](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918536086) (option)

The **Dependencies** button controls the visibility of the dependency links on your Gantt timeline. Check the box next to the dependency type you want to see and how:

### Category

- Strong
- Soft

### Display

- Expanded
- Collapsed

### Browse dependencies

Check this option to open the **Dependencies** tab in Gantt’s **[Infobar](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918800450)**.
</details>

# Taskbar (new navigation)

<details>
<summary>Click to expand the guide</summary>

## Overview

The taskbars on the [Gantt timeline](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918701893) (Gantt chart) represent your project work items (for example, epics, Jira work items, and [BigPicture tasks](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918405930)).

Each taskbar can immediately provide you with the following information:

- Task start/end dates
- Color (by default, the color is based on the task status)

![Screenshot of the taskbar in the Gantt module.](media://8345e48b-02fe-46bd-9c0a-743b7d43edd1)

If the task is scheduled or partially scheduled (it has only a start or end date), it will be visualized as a taskbar on the Gantt timeline. 

- The beginning of the taskbar marks the start date.
- The end of the taskbar marks the end date.
- If the start/end date is not defined, the relevant side of the taskbar is faded.

If you cannot see the exact date,[ zoom in](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918701893/Timeline+Gantt+chart#Zoom-in%2Fout) on the timeline or [snipe to its start/end date](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918701893/Timeline+Gantt+chart#Snipe-to-task-start%2Fend-date).

You can add an additional layer of information to the Gantt timeline by selecting the relevant option from the **View** and **Indicators** menus. 

![Screenshot of the View and Indicators menus highlighted in the Gantt module.](media://53429864-6f99-4cb3-b3c1-0c45818ee566)

## Indicators (option)

1. Click **Indicators**.
2. From the menu, check one or several options:

- Baselines
- Markers
- Timeboxes (Sprints, PIs)
- Week numbers
- Parent task conflicts
- Progress
- Critical path
- Overdue tasks

![Screenshot of the Indicators menu expanded in the Gantt module.](media://9ae5812e-02fb-4d0a-81c4-ccfcf39f6b95)

### [Baselines](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918404564)

If you have baselines created for your tasks, they can be displayed as horizontal lines under the taskbars.

![A baseline under a taskbar.](media://cee75553-2067-490f-94d5-7a4c48c79a75)

### [Markers](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918699490)

Markers highlight important dates, such as events or deadlines. 

![Screenshot of markers in the Gantt module.](media://b2bec379-1ce9-439d-b5fc-1d8b1e84eb14)

### Timeboxes (Sprints, PIs)

Check the option to see timeboxes on the Gantt timeline.

![Screenshot of enabling timeboxes on the Gantt timeline.](media://d07148aa-3335-449c-989f-0325998a502d)

### [Week numbers](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918801444)

The timeline displays days, months, quarters, and years, but you can also enable weeks if you plan to use weeks.

### [Parent task conflicts](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918832897)

The **Parent task conflicts **option adds a yellow overlay to the taskbar to indicate a mismatch between the task's period and that of the child or parent task.

![Period warning on the taskbar.](media://307c7c32-5f26-458a-ac2c-1c987ca17ab5)

### Progress

The taskbar color gradually fills up as the progress advances.

![Progress on the taskbar.](media://2740b3df-9abb-4ad7-838a-700caa38272a)

### [Critical path](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918405060)

If you have created dependencies between the tasks, this option will change the color of the tasks on the critical path to red stripes. 

![Taskbar on the critical path.](media://10caa146-b60c-417d-aa13-d3f656d7de27)

### [Overdue tasks](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918537803)

Enable this option to see tasks that were not completed on their due date. The color of the due taskbars changes to red, and the number in a red circle indicates the number of due days.

![And overdue taskbar.](media://a259009b-c47d-4efe-b657-504188bd3623)

## View > Task labels (option)

1. Click **View > Task labels**.
2. From the menu, check one or several options:

### Label position

The **Label position** determines where the task summary will be placed in relation to the taskbar. The task label can consist of the Key and/or Summary field values. 

> 📝 You must first check the **Key** and/or **Summary** in **View > Task labels > Show**.

- Hidden (Removes the label, leaving the taskbar blank (but still colored).
- On the taskbar (displays the label on the taskbar. If the label is longer than the taskbar, the label is truncated).
- Next to the taskbar (displays the label on the right side next to the taskbar).
- Smart labeling (displays a summary on or next to the taskbar, depending on whether the summary exceeds the taskbar length).

### Show

The **Show** options add more info on/next to the taskbar.

- Key [taskbar label]
- Summary [taskbar label]
- Other scope info (adds an indication on the taskbar when a task is in the scope of multiple boxes)
  - **Note**: This taskbar indication applies only to boxes of the **own** [scope type](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918766536). If a task is in the scope of a sub-box, it belongs to multiple boxes but not multiple own-scope boxes.

- Dates
- Assignee (adds the assignee avatar/icon)
- Priority (displays the priority icon taken from the built-in Priority field on the left side next to the taskbar)
- [Scheduling mode](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918831395) (displays the scheduling mode icon on the left side next to the taskbar)
- [Notes](https://appfire.atlassian.net/wiki/spaces/SPM/pages/2372665547)

### [Task color](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918636160)

Colors the taskbar by its status or by manually selected colors.

## View > [Dependencies](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918536086) (option)

The **Dependencies** button controls the visibility of the dependency links on your Gantt timeline. Check the box next to the dependency type you want to see and how:

### Category

- Strong
- Soft

### Display

- Expanded
- Collapsed

### Browse dependencies

Check this option to open the **Dependencies** tab in Gantt’s **[Infobar](https://appfire.atlassian.net/wiki/spaces/SPM/pages/1918800450)**.

![Screenshot of the Dependencies menu expanded in the Gantt module.](media://6665b256-9cbe-40d6-b24c-0a7a0248d8c9)