## About the Plan delay report

Plan delay reports provide information on task delays on all hierarchy levels, with a set **Baseline End Date **field.

![Plan delays window with one row highlighted](media://4a336a9a-7dfc-4131-84bf-b02a353029df)

Hold the pointer over a task name to display a tooltip with the task's status in round brackets.

Tasks are sorted by **End Date. **

## **Report configuration **

In the plan delays report, you can edit the report configuration to:

- show **only the open delayed tasks **versus the plan - to monitor current delays
- show the **closed delayed tasks** - to check the number of delayed tasks versus the plan after finishing the project

![Plan delays window with no data](media://a302cf62-ec5c-488d-ab30-1e4cda33b6b1)

![Plan delays window with template created](media://8cb2edd7-de60-4942-b8aa-be2b7dabea78)