## Track the progress of priorities

### Tasks and goals 

You can track the progress of prioritized tasks (Jira work items) and goals (OKRs) by switching to the predefined **Priorities column view** in the **Gantt and Scope modules** or by adding the **Priority score** column to the module view.

Recommended use of the Priority score column in the Gantt module:

- Use the Priority score column during planning to focus on high-impact tasks and goals and ensure your efforts are aligned with key priorities.
- In status sync meetings, use the Priority score column to stay informed about potential blockers in high-priority initiatives and swiftly adjust delivery plans throughout the year.

### Boxes

You can track prioritized boxes by adding the **Priority score** column to the Overview module.

![image-20250710-083841.png](media://42c343ba-d9a1-4ab5-b13f-413574780bc2)

## Predefined Priorities column view

To enable the predefined **Priorities** column view in the Gantt module:

1. Go to the Gantt module.
2. Expand the column view dropdown menu.
3. Select **Priorities**.
4. Once applied, you can track priorities using the Gantt module.

## Priority score column

You can add the **Priority score** field to a column view in the Overview, Gantt, Scope, Board Backlog, and Risks modules. 

![Screenshot of adding the Priority score to the column view in the Gantt module.](media://367cffe3-5608-4650-a376-c4690b50b1f5)

### Inline edit Priority score details 

To inline edit Priority score details:

1. Click the **Priority score value**.
2. Inline edit values in a new window.
3. Click the **Go to priorities** button to move to the** Priorities** **module**.

### Customize the Priority score column in Gantt and Scope

When you add the **Priority score** column in the Gantt and Scope modules, you can customize it using the following actions:

- Pin column
- Sort tasks
- Customize aggregation and display options
- Resize all columns to fit
- Remove column

![Screenshot of customizing the Priority score column in the Gantt module](media://61712ca5-9276-4470-b301-b05ea98029fb)

#### Sort by the Priority score column 

Sort tasks and initiatives by the Priority score column to see the most important tasks at the top of the Gantt structure. 

![Screenshot of sorting tasks and initiatives by the Priority score column in the Gantt module.](media://6077c46d-1966-4ec9-a3c0-5d3a02ea5ad6)

### Jira Priority column

The priority scores you assign to your tasks do NOT affect the Jira native **Priority** column. You can manually inline edit the Priority column in the Gantt and Scope modules.