title: "Resolving BigPicture and Jira Sprint Date Synchronization Issues"
canonical: "https://support.appfire.com/space/SUPPORT/3504439698/Resolving%20BigPicture%20and%20Jira%20Sprint%20Date%20Synchronization%20Issues"
format: markdown
---
This article explains how to resolve a synchronization issue where sprint dates in BigPicture do not match the dates in Jira, specifically when the **Automatic sprint-based timeboxes** option is enabled. It covers the scenario where timeboxes become read-only in BigPicture and provides a workaround to force a resynchronization.

## Problem/Context

When a BigPicture Box is configured with **Automatic sprint-based timeboxes**, the app treats the sprint dates as being managed exclusively by Jira. Consequently, these timeboxes become read-only within BigPicture.

Users may encounter a situation where the dates displayed in BigPicture are different from those in Jira. If a user attempts to manually correct the dates in BigPicture, they will receive the following validation error:

> **Validation Error:** Cannot update box [Box-ID] when Automatic sprint-based timeboxes option has been enabled. You can edit sprints in Jira or change timeboxes settings in the box configuration.

## Cause

This mismatch typically occurs when the synchronization between Jira and BigPicture fails to trigger or complete after a change is made to the sprint dates in Jira. Since the "Automatic" setting locks the fields in BigPicture, the UI prevents manual overrides.

## Solution/Workaround: Force Resynchronization via Jira

To resolve the date mismatch and force BigPicture to update its records, follow these steps:

1. **Navigate to Jira:** Go to the Jira board where the affected sprint is located.
2. **Edit the Sprint:** Open the sprint details and make a minor change to the sprint dates (e.g., change the end date by one day and then change it back, or simply re-save the existing dates).
3. **Save Changes:** Saving the sprint in Jira triggers a synchronization event.
4. **Verify in BigPicture:** Return to BigPicture and refresh the page. The dates should now be correctly synchronized and match the Jira sprint dates.

### Related Documentation

For more information on how automatic timeboxes work, please refer to the official documentation:  
<u>[BigPicture Documentation - Timeboxes (Synced with Jira Sprints)](https://support.appfire.com/space/DLP/2211746298/Timeboxes#Automatic-timeboxes-%28synced-with-Jira-sprints%29)</u>